The much-awaited Noida International Greenfield Airport in Jewar is set to miss its third deadline of May 15 set by Uttar ...
YIAPL, Tata Projects Limited and NIAL apprised the chief secretary about the progress in construction of runway, terminal ...
Registration open from April 21 to May 21, 2025; as many 276 plots available for allocation through draw by YEIDA ...
UP Chief Secretary Manoj Kumar Singh has directed all pending work at Noida Airport to be completed by June 30, with the ...
During the inspection, it was found that while the second roof of the terminal building was 75% complete, work on floor ...
The Noida International Airport project has missed its third deadline, with the 15 May date for domestic operations now ...
According to the reports, the airport is unlikely to open within the next two months, putting the project over a year behind ...
Uttar Pradesh Chief Secretary Manoj Kumar Singh on Wednesday took stock of the construction work and preparations at the Noida International Airport, Jewar. Singh told officials at a meeting held on ...
Noida: The much-awaited Noida International Greenfield Airport in Jewar is set to miss its third deadline of May 15 set by Uttar Pradesh Chief Minister Yogi Adityanath. The new deadline for flight ...